Key Data
- The building and the system design were analyzed, constructed and optimized.
- A comprehensive list of EE features was integrated in the project tender.
- Computer Modeling:
- Energy Index estimated less than New Energy Code target (Malaysian Standard MS 1525:2001).
| Energy Index estimation |
= 100kWh/m2/yr. |
| Proposed by New Energy Code |
= 135kWh/m2/yr. |
| Average Office Building in Malaysia |
= 200-300kWh/m2/yr. |
- Economic feasibility of Low Energy Offices documented 50% energy saving and less than10 years payback.
- Based on a Positive and Fruitful Cooperation between MEWC, the PJH Team, JKR Putrajaya Team, Main Contractor and the DANIDA Team.
- The building have been completed and occupied in mid of September 2004
- The LEO building has been occupied in mid of September 2004.
- A lot of re-commissioning and fine tuning works has been done.
- The Building Energy Index have been monitored from time to time and the latest index is shown as below;
|
|
 |
|